Iona
Iona
Location: University of British Columbia, Vancouver
Completion: January 2016
General Contractor: MRC Total Build
Value: 1,000,000
Scope of Work: Working as a subcontractor to MRC Total Build we completed an extensive renovation to an existing building previously occupied by Vancouver School of Theology. New UBC user is Vancouver School of Economics (VSE). New Lecture Hall, meeting rooms, office upgrades, classrooms and computer labs are a few of the spaces that were upgraded. Scope of work included lighting / lighting control, emergency lighting, fire alarm, power systems upgrades. Conduit Infrastructure for card access / communication / audio visual were also upgraded.
Iona also has student dorms which were upgraded as well as part of this project. New floor panels and distribution work including kitchen upgrades.
UBC Henning
Hennings Building - Lecture Room 200 Renovatior
Location: University of British Columbia, Vancouver
Completion: September 2017
General Contractor: Halse-Martin Construction Ltd
Value: 250,000
Scope of Work: Working as a subcontractor we completed a complete electrical renovation to an existing lecture hall.
Complete conduit and wiring upgrade for all power systems, new lighting fixtures and lighting controls.
New panel board and feeder install, conduit run was lengthy and had to be run through existing building with minimal disruption.
The project included a tight time line as work needed to be completed during the summer break, which brings the challenges of ordering and receiving long lead time items (lighting fixtures) with enough time to install.
UBC Life Sciences
Life Science Center – High Plume VFD Project
Location: University of British Columbia, Vancouver
Completion: Sept 2015
Value: 350,000
Scope of Work: Working as a prime contractor we performed this complex Variable Frequency Drive motor control work for the Life Sciences Centre- High Plume system. Project involved installing new drives / ground bushings and wiring on existing high plume exhaust motors which service the exhaust hood for the labs throughout the building. Careful planning of work had to be coordinated and performed from beginning to end as to the hazardous air and need for the system to have minimal shutdowns. Work was undertaken in very short timeframes under complex / enclosed working conditions.
As the motors are installed in the high plume cones could not be removed easily, we came up with a scaffolding system, confined space safety program, air breathing system, and removal system for our personnel. The work performed was similar to ocean diving in an exhaust duct.
All new VFDs needed new control conduit / wiring completed on roof with rigid conduit.
Notre Dame Senior Secondary School
Notre Dame Senior Secondary School – Infill Project
Location: Vancouver, BC
Completion: April 2015
General Contractor: Gauvin Construction Ltd
Value: $300,000
Scope of Work: Working as a subcontractor to Gauvin Construction Ltd we completed electrical to a new infill building on an existing senior secondary school. Work included new panels / feeder cables, lighting fixtures and controls to new general teaching classrooms, food / cooking classrooms, cafeteria and gym area.
Douglas T Kenny Building
Douglas T Kenny Building – Mechanical Upgrade
Location: University of British Columbia, Vancouver
Completion: October 2018
General Contractor: Division 15 Mechanical Ltd
Value: 250,000
Scope of Work: Working as a subcontractor we completed a mechanical wiring upgrade throughout the building. Ceilings were removed for the install of a new ventilation system which included removal and re-installation of all electrical in ceilings spaces.
Project included the supply & install of a new back up generator, automatic transfer switch and ion meter installation. The install of the generator into the building took special coordination and planning due to the space restrictions in the existing site conditions.
Museum of Anthropology
Museum of Anthropology – Masterworks Gallery
Location: University of British Columbia, Vancouver
Completion: May 2017
General Contractor: Holaco Construction Ltd
Value: 350,000
Scope of Work: Working as a subcontractor to Holaco Construction we completed a complete electrical renovation to an art gallery room. This gallery houses historical Indigenous artifacts. The focal point on this project was the lighting application which luminates the artwork. The lighting was designed to mimic the ever changing natural exterior light. Steele Electric is proud to have worked with all parties including the design team / UBC Project Services / UBC MOA staff / Holaco Construction.
UBC Koerner Building
UBC Koerner Building – 7th Floor Renovations to the Presidents Offices
Owner/Client: UBC Project Services
General Contractor: Holaco Construction Ltd.
Value: $140,000
Scope: Renovation to entire 7th Floor for new offices, conference rooms, meeting rooms, waiting areas and lunch room. New LED energy efficient lighting fixtures & new power distribution throughout. Communication / Audio Visual conduit infrastructure.
Cascades Casino Parkade lighting upgrade with daylight harvesting. This projects helps to power 22 homes for an entire year! From design, implementation, securing rebate funding from BC hydro, we take pride in our work while providing customers with the best service and value on every project regardless of size.
Casino Exterior Lighting Upgrade
Cascades Casino Exterior Lighting Upgrade (Power Smart Upgrade)
Owner/Client: Gateway Casinos & Entertainment
Value: $75,000
Scope: Complete exterior site lighting & convention area upgrade to reduce energy consumption, improve lighting levels and reduce maintenance costs in the future. Supply & Install Douglas Lighting Control System.
Olympic Dining Hall
Olympic Dining Hall Vancouver & Whistler
Owner/Client: PKL Group
Value: $850,000
Scope: Provide Design & Install of Power to 2 Temporary Dining Facilities for the 2010 Vancouver Winter Olympics. Supply & Install distribution transformers & panels to power kitchens / coolers to feed athletes and workers for the games.